If you check the email, it looks like we've been given some grace for milestone 5. So here's what our plan should be.
Tomorrow (11/13)
-Permanently hook up levitation circuit.
-Address balance issue and mount NXT and Batteries (How about a strip of velcro down the two sides covering the whole length, so we can freely move the batteries?)
-Hook up propulsion circuit and test propulsion fans
-Complete milestone 5 part 1 and 2
Tuesday (11/18)
-Install LEGO sensors
-Hook relays to the NXT
-Test control algorithm
-Complete milestone 5 part 3
What do you guys think? We're well on our way to having a completed hovercraft!